Deck Membrane Replacement, April 2013, Edmonton

This residential client reached out to GRS to replace the membrane of their home's decking system. GRS ensured that everything was done to specification, in addition to some light repairs on the client's garage roof.   Quotation Delivered: February 26, 2013 GRS delivered a quotation for the membrane replacement on their existing deck that sits above a living area. The existing membrane would need to be removed and replaced with a new SBS system and some drains to accommodate the water ponding.   Client Correspondence: March 28, 2013 We sent word out to the client that the senior journeyman roofer would be attending the site this day around 5:00pm to go over the installation specifics. The journeyman was briefed ahead of time to understand that the scope of the work covered removing the existing membrane to the decking, then apply a 2-ply charcoal SBS Modified roofing system. If further work needs to be done to adjust slope or substrate repair; the journeyman will be able to assess the situation at that time.   Roof Report: April 8, 2013 A previous report (consisting of the membrane removal) is, unfortunately, no longer available. Work description: The crew arrived on site to continue with the deck surface replacement, so they started by removing the wood siding's first (bottom) row, and tarred the existing two layers of decking. The rest of the deck was the cleaned up and the gravel stop prepared for the new membrane. With that complete, they installed a layer of IKO Armourbond Flashing on the deck, including all corners and up the wall to 8" height.   image006image001 image002 image003 image004 image005         Roof Report: April 9, 2013 The garbage was all cleaned up, picked up, and disposed of before the crew got to the torch-on capping. As with all open-flame procedures, there was a fire watch protocol to carry out, so the team waited on-site for the prescribed time, working on sheet metal over the nearby garage in the meanwhile. Spots and laps were caulked to shore up the watertightness of the area.   Roof Report: April 11, 2013 The crew began by removing four old drains and replacing them with new ones. Shortly after, they moved to cut away the base sheet from the gravel stop and stripped it in correctly. Then, the cap sheet was cut and prepared for the following day. The crew had to seal up all of the exposed seams to waterproof it properly, before the cap sheeting could be applied.   20130411_114641 20130411_114656 20130411_163306 20130411_171017     Roof Report: April 12, 2013   This day, the crew used seven full rolls of SBS (black) cap sheeting and half of a roll of base sheet on the decking area. The four new drains were installed and the siding that had been removed some days earlier was replaced and installed into its original place.   Roof Report: April 13, 2013 All of the cap sheet was torched and installed to specification, and the site cleaned up of garbage. With the garbage disposed of, the project was now considered complete. 20130412_154320 20130412_154353     Warranty Repair Request: July 28, 2014   The client reached out to GRS to request an inspection on an area of the decking that was damaged during a patio door installation. Now, the deck appears to be leaking into the room below, and they would like it repaired. GRS booked a technician to go on-site the following day to see what needed to be dealt with.   Inspection: July 29, 2014 The technician went out to the client's location and began inspecting the decking area. There were some damaged spots, but (fortunately) none of them appeared to be a through-and-through puncture into the membrane. Upon visual inspection, the leak could be traced to a certain degree of accuracy, but the area underneath the new door is inaccessible without removing the doorframe around it. GRS delivered a new quotation for the repairs, and this report will be updated if/when work continues on this site.   Photos: Service Follow-up, October 21, 2015 Some additional photos were submitted to show how the canopy was holding up. They're embedded below. 20151021_112537 20151021_113656 20151021_120330 20151021_120544 20151021_120601 20151021_120606     CODE: 14107 Contact Us Call our 24 hour emergency roof repair at 1.780.424.7663. Mail to: 3428 99 Street NW Edmonton, Alberta T6E-5X5. We service all of Alberta including Edmonton, Stony Plain, Spruce Grove, Fort Saskatchewan, St Albert, Sherwood Park, Leduc, Nisku, Beaumont, Lac La Biche, Grande Prairie, High Level, Westlock, Slave Lake, Edson, Drayton Valley, Devon, Camrose, Wetaskiwin, Tofield, Lamont, Morinville, Vegreville, Millet, Calmar, Evansburg, Redwater, Onaway, Viking, Athabasca, High Prairie, Valleyview, Fairview, Peace River, Whitecourt, Mayerthorpe and many more rural areas and towns.

Edmonton Roof Deck Replacement and Waterproofing, October 2011

This residential client was provided with a quotation for the replacement and re-installation of a proper decking and waterproofing system. There is water leaking into the home and proper draining systems need to be installed. This report also includes a follow-up service call. Inspection, October 8, 2011:
The client is looking to have both decks re-surfaced and proper drain systems installed. There is moisture getting into the home in the daughters room. There is also dimpling visible on the ceiling and screws were dropping down, those have since been plastered over. Both decks are pooling water and are improperly sealed. The client believes there is stucco below the deck and has questions about damage to it or the foundation during the process. The client is also looking to have new eaves-troughs installed.
DSCF0709 DSCF0710 DSCF0711 DSCF0712 DSCF0713 DSCF0714 DSCF0715 DSCF0716 DSCF0717 DSCF0718 DSCF0719 DSCF0720 DSCF0721 DSCF0722 DSCF0723
Roof Report, November 27, 2011:
I am unable to give as much slope to the decks as the customer would like as the threshold under his doors is only 1" after I rip the old roof off. I plan on using sloped fiberboard around the wall lines as this will only build it up by .5" and give some sort of slope at the walls. As the threshold is only 1" under the door I don't want to use FR board because this will build the roof up too much. Instead, I plan on using the fast and stick 180 base-sheet as this is mechanically fastened and can be used directly on the plywood deck. Along the wall lines the stucco starts 1" above roof line. In order to be able to ensure a good seal I want to put plywood strips along the wall line at the height of 4" to give me plenty to seal to on the walls. To make this look better for the client I would like to use a black metal flashing over my wall line cap-flashing (to make it look more like crown molding, and it will match the metal cap at the top of the wall). The door provides me with a bigger problem. I would like to run my cap flashing up onto the door sil as this will give me more to seal to instead of trying to work under it as it is only 1". As I know using the torch on his door sil presents a real fire hazard, I would like to use a peel and stick 250 cap with the IKO S.A.M adhesive and a detail roller.
101_0002 101_0003 101_0004 101_0005 101_0006 101_0007 101_0008 101_0009
Roof Report, November 30, 2011:
We ripped off the larger of the two roofs at the back side of the house. Once the old membrane was ripped off we inspected the plywood deck, the plywood was wet but not rotted out in any spots. After the plywood was inspected we put our plywood strips around the perimeter of the building to allow me the height I need to seal my ply's. Once the plywood was installed we cut fiber board on a 45 degree angle and screwed it along the perimeter to create as much slope as the threshold under the door would allow. Once the fiber board was screwed down we laid out our rolls of fast and stick 180. Then we screwed it down for our first ply of the system and torched the laps to make it all water tight. This morning we lost a couple of hours removing snow and chipping ice. After we got all the snow and ice removed from the roof we primed half of the perimeter. I put on the armourbond flash up the walls and sealed it to the top of the plywood to ensure a strong seal. After I finished the flashing I was able to put down half of the 250 cap sheet on the flats of the roof. Once that was done i degranulated the perimeter and moved all of the customers belongings on the deck to the completed side so I can get a good jump start in the morning.
101_0033 101_0034 101_0035 101_0036 101_0037 101_0038 101_0039 101_0040 101_0041 101_0042 101_0044 101_0051
Roof Report, December 4, 2011:
I went to work on the front deck of the house, we ripped off the old membrane and inspected the plywood deck for rotten areas but none were found. As with the back deck the plywood was found to be wet but not damaged in any areas. After we dried the plywood as best as possible, we built the plywood walls around the perimeter to allow me to seal my ply's. Once the wall lines were installed, we used strips of fiber board cut at a 45 degree angle to create as much slope as the threshold around the door would allow. Then we screwed it down. After the fiber board was laid out I was able to lay all of the 180 fast and stick base sheet over all the flats, screwed it all down, and torched all of the laps. Next the plywood wall lines were all primed so I could put my 180 capping on the walls. I was able to cap half of the wall with 180 peel and stick capping, starting from the drain and working out. To make things easier for our next day I torched down my first run of the 250 cap sheet on the flats.
101_0065 101_0066 101_0067 101_0068 101_0069 101_0070 101_0071 101_0072 101_0073 101_0074101_0076
Roof Report, December 12, 2011: This morning we returned to the client's house to continue work on his roof decks. After we finished drying the roof I completed all of the peel and stick capping around the perimeter including under the doorway. Once the 180 capping was complete I finished the flats with the 250 cap sheet, and finished degranulating the perimeter of the 250 cap sheet. I was also able to complete about 40% of the 250 capping along the wall lines. All I have left on this roof is to finish the 250 capping around the wall and put all of the customers furniture back where it was when we showed up. I plan on drying the smaller roof in the morning and then ripping it off first thing.
101_0054 101_0055 101_0056 101_0057
Follow-up Service Call, March 14, 2012:
Arrived at the site and the client showed us the water damage in both of her children's rooms, however there was no water damage in the bathroom between the two rooms.  After inspection of the SBS roof, there were a few blisters starting. These blisters were not attached to any exterior wall or opening in seams, so we suspected that it was moisture underneath the membrane and not a leak from roofing system causing the blister. We discussed with the client that because of the ice on the roof it would be best not to continue the blister repair at this point. Client mentioned that her husband was shoveling the snow off the deck as a preventative measure, which may or may not indicate any attempt to clear the drain. We did suggest that we could conduct a flood test to give the client peace of mind. This would test whether any rain in the meantime would leak from our drain installation. The customer agreed and gave permission for the flood test and remained just inside the home with an open door between us and her. We conducted the flood test and initially there was no moisture coming through where previous leaks occurred.  However, after 30 minutes of flooding the roof on deck, the clients nanny told us that there was a water leak in the kitchen, the floor beneath the original leak locations. At this time we turned off the water. As we came downstairs to inspect the new leak, we suspected that the leaks were not caused from a leak in the membrane on the deck, nor was the problem just a leak around the drain area.  The leak in the kitchen was substantial and furthermore there was water running down over the back entrance on the exterior wall.  After noticing this we went back to the original leak areas (ie. the children's bedrooms) above the kitchen, at which time we noticed that the floor was getting wet in the bedroom directly above the kitchen. We noticed the sound of dripping water while standing in the bathroom between the two bedrooms, client was present when mentioning the sounds coming from inside the walls. It is our conclusion that for this amount of water to penetrate such a large area of the house in such a short time frame the water must be coming from the drain pipe. It is attached to the drain bowl which is enclosed in the wall and exits the exterior wall between the first and second floor (ie. between the kitchen and bedroom directly above). At this point we told the customer that this was not a roofing problem, and that she had a drain problem which would require a plumber. We further advised her that this is not warranty work, any problems to roof assembly that have occurred because of the drain problem would be addressed after the plumbing problem is fixed and would then be chargeable work as our warranty is void if there is an already existing issue outside of the scope of our work.  She is also aware to e-mail GRS with the progress and completion of such work.
March 14 028 March 14 029March 14 031 March 14 032 March 14 033 March 14 034 March 14 035 March 14 036 March 14 037 March 14 038 March 14 039 March 14 040 March 14 041 March 14 042 March 14 045
Roof Report, March 15, 2012:
Arrived at clients home and inspected both drains. First drain inspected while the client poured water down the drain. Fairly steady drip came from seal from the inside of the bowl. The second drain was inspected from open ceiling and the leak was not the bowl itself but the insert attached to the bowl had a horizontal split which was the cause of a substantial leak. We are not certain as to who installed what in this plumbing section. Inserts do need to be changed out. To temporarily fix the leaking we caulked the split on one drain and caulked the ridge of the compression ring on both drains.  We explained to the clients that it is a temporary fix until further action is taken on the part of GRS or a plumber. The split could be a manufacturer default or a crack which was then split from freezing water, or it could be due to someone trying to clear the drain with an object. These are just possible reasons for an uncertain situation and speculation based on the fact that the crack was horizontal. We explained that once the deck is dry and a course of action is decided upon, the drains will be repaired and the blisters would be fixed at the same time.
11230 77 Ave 001 11230 77 Ave 002 11230 77 Ave 003 11230 77 Ave 004 11230 77 Ave 005 11230 77 Ave 007 11230 77 Ave 009 11230 77 Ave 015 11230 77 Ave 016 11230 77 Ave 020 11230 77 Ave 025 11230 77 Ave 033 11230 77 Ave 035 11230 77 Ave 040 11230 77 Ave 044
Service Follow-up, April 1, 2012: The following email was sent by the client to our project manager:
I have water flowing into my great-room, over the deck (currently out of 2 spots at a great rate of flow). There are wet spots all along the path likely leading to the drain area in the front.  The back deck remains ok, with no drainage, but covered up with the tarp still.  The areas fixed on Thursday look intact, but the edges of the repairs are mixed with water and the "fix it material". I have photos and video.  This is similar to what happened in Dec after the original remediation on the decks which supposedly stopped the issue. He told me at the time it was likely an interface with the drain issue that he was able to stop with some caulking. Any thoughts or suggestions on stopping this flow and ongoing issue?
Following this email a crew member was sent out to inspect the leaks, the inspection notes are below:
Client indicated the leak is a very small amount of water that only leaks during a heavy rain fall. The amount is about two to three table spoons of water. The leak comes off of a truss. The client has caulked the metal around the balcony on the bottom which has solved prior leaks.
We flood tested on top of the metal where it was caulked and we attempted to flush water up behind the metal.  The truss started to get moist.  We re-caulked the fastener heads and the old caulking. There may have been pin holes in the caulking. If this doesn't stop the leak then the metal flashing may have to be removed to diagnose the leak further. The roof is wet due to rain and there is rain in the forecast for this afternoon. The client is happy with the trouble shooting and is willing to wait and see if the leak has stopped. There are three buckles that will need to be addressed in the near future.  This can be done with ms detail and grey granules, weather permitting.
IMAG0544 IMAG0545 IMAG0551 IMAG0553 IMAG0554 IMAG0556 IMAG0557 IMAG0560 IMAG0561 IMAG0562 IMAG0563
< End Report > CODE: 11230 Contact Us Call our 24 hour emergency roof repair at 1.780.424.7663. Mail to: 3428 99 Street NW Edmonton, Alberta T6E-5X5. We service all of Alberta including Edmonton, Stony Plain, Spruce Grove, Fort Saskatchewan, St Albert, Sherwood Park, Leduc, Nisku, Beaumont, Lac La Biche, Grande Prairie, High Level, Westlock, Slave Lake, Edson, Drayton Valley, Devon, Camrose, Wetaskiwin, Tofield, Lamont, Morinville, Vegreville, Tofield, Millet, Calmar, Evansburg, Redwater, Onaway, Viking, Athabasca, High Prairie, Valleyview, Fairview, Peace River, Whitecourt, Mayerthorpe and many more rural areas and towns.

Edmonton Residential Roof Deck Waterproofing Inspection, July 2011

This client required a quotation for various waterproofing options to fix a leaking deck. Our crew was dispatched to provide an inspection and to determine where the leak was coming from. Inspection, July 27, 2011: I arrived on-site and the client took me to the garage and showed me where water was still dripping down from yesterday’s rain. They have the drywall and insulation stripped in the area where the drain comes down from the flat roof. I set my ladder up on the cross beam that runs across the garage. I was facing the entrance to the house. The floor joist runs just to the right of the roof drain, it is spliced on the cross beam that I had my ladder leaned up against and it appeared to be soaked between the two joists on the splice. The splice and also a very short piece of 2x4 about 2” long appears to be screwed to the deck from above. When I stuck my finger between the 2x4 and the joist it was saturated, this is the area where the water is coming in. It is within a foot from the drain area but the drain or drain pipe itself was not wet at all after running a water hose down it to test it. The client did say that the water does not come through right away when it begins to rain so the leak may not be in the immediate area but I am convinced it is coming from the flat roof. I inspected the shake roof surrounding the flat roof but didn’t find anything that I felt would be the problem.
100_1209
The inspection of the drywall and insulation revealed that the entire assembly was saturated with water from leaks.
100_1210
The technician's ladder was setup on the crossbeams across the garage. From this view, our technician was able to inspect the floor joist that ran just to the right of the roof drain.
100_1212
After inspecting the flat section of the client's roof, the technician could not easily surmise what was causing water ingress.
This report may be updated at a later time. < End Report > CODE: 419 Contact Us Call our 24 hour emergency roof repair at 1.780.424.7663. Mail to: 3428 99 Street NW Edmonton, Alberta T6E-5X5. We service all of Alberta including Edmonton, Stony Plain, Spruce Grove, Fort Saskatchewan, St Albert, Sherwood Park, Leduc, Nisku, Beaumont, Lac La Biche, Grande Prairie, High Level, Westlock, Slave Lake, Edson, Drayton Valley, Devon, Camrose, Wetaskiwin, Tofield, Lamont, Morinville, Vegreville, Tofield, Millet, Calmar, Evansburg, Redwater, Onaway, Viking, Athabasca, High Prairie, Valleyview, Fairview, Peace River, Whitecourt, Mayerthorpe and many more rural areas and towns.