Flat Roof Repair Calmar Alberta, June 4, 2015.

Article: EPDM Flat Roof Repair Calmar Alberta, Commercial Building, Slope Toward Drains.

Below you will find a report from the flat roof repair crew. The issue with this roof was that a back-slope was required to get the water drainage correct. Once the back slope was installed on the flat roof the water drained from the roof much better. May 9, 2015: Crew Arrives to Complete Repair 
EPDM Roof
This EPDM roof had significant water ponding at the edges and drainage issues. 
Water Pooling
Technicians removing water from the roof to prepare for the back-sloping.
Installing EPDM
Installing EPDM over newly sloped area for more effective water drainage.
EPDM Repair
EPDM Repair in progress. Installing a back-slope at the roof parapet to redirect water to drain.
  After filling out our safety documentation and a weekly safety meeting we went up on the roof to find about 2 inches of standing water along the back wall. We spent 2 hours getting the roof dry. Once the roof was dry we then installed our slope with screws and plates to correct the roof ponding issues. After that we put 3 inch seam tape around the perimeter of our back slope. Once that was complete we put latex in our rubber using 2  pieces as one piece. It would of been a hassle after we glued our rubber down. The crew then glued it to the seam tape all around to ensure a 100% seal. The slope turned out really good. The customer inspected the work and was happy. I also noticed 2 outside corners that where failing so I fixed them while I was there we then packed up our tools downloaded them to the truck and left site at 5 PM. More Photos of Completion of Roof Re-Slope Repair. 
EPDM Flat Roof Repair
Applying an EPDM patch to a failed corner.
EPDM Repair
EPDM Repair completed - back-slope at parapet wall completed to ensure positive drainage of this flat roof.
  < End Report > Code: 5120 Contact Us Call our 24 hour emergency roof repair at 1.780.424.7663. Mail to: 3428 99 Street NW Edmonton, Alberta T6E-5X5. We service all of Alberta including Edmonton, Stony Plain, Spruce Grove, Fort Saskatchewan, St Albert, Sherwood Park, Leduc, Nisku, Beaumont, Lac La Biche, Grande Prairie, High Level, Westlock, Slave Lake, Edson, Drayton Valley, Devon, Camrose, Wetaskiwin, Tofield, Lamont, Morinville, Vegreville, Tofield, Millet, Calmar, Evansburg, Redwater, Onaway, Viking, Athabasca, High Prairie, Valleyview, Fairview, Peace River, Whitecourt, Mayerthorpe and many more rural areas and towns.

Residential Flat Roof Repair Edmonton, June 9 2015

Article: Residential Flat Roof Repair Edmonton, Alberta. EPDM Low Slope Roof Membrane.

Repair of an EPDM low slope roof on a residential home in Edmonton, Alberta. The low slope (flat) roof transitions to a pitched shingle roof. Penetrations and challenges include chimney, skylights, vents, drainage, ice damming, and insulating value on low slope. Additionally the transition between the low and steep roof systems posed challenges. Also a section on choosing the correct low slope membrane and roof assembly.
This customer had originally called us when Edmonton had set records for snow-fall in January of 2012. She had significant snow loads on her roof and the concern was that her roof may collapse. So we removed the snow from her roof and discovered significant ice damming challenges on the low slope portion.
We returned in 2013 and 2014 to do regular roof snow removal because every-time the snow built up on the roof the heat from inside her home would get to the underside of the low slope roof sheathing and cause ice damming. The ice dams would then get in between the laps of the existing roof membrane and result in leaks.
Mid 2014 she contacted us to quote on the replacement of the low slope roofing with hopes of solving the problem.
We quoted the various options for low slope roofing membranes, which included; Spray Foam (SPF), Tar and Gravel, SBS Torch-On, EPDM, TPO, PVC and Liquid Rubber.
Our standard quotations include pricing for the different options available for flat roof system membranes, a roof inspection report, a write-up on the pro's and con's of each type of system and our recommendations for your most suitable roof membrane choices.
Below is a sample flat roof quotation. The first link is a PDF download and the second is a Word Doc file download.
Our customer chose to replace her failing tar and gravel built up roof with an EPDM single ply membrane roof recovery (or retro-fit). This means that we removed the gravel and skinned the bitumen membrane off and then mechanically fastened a roof board and then fully adhered the EPDM. We also did some drain work and scupper work. Our customer did not opt for a complete removal, re-sloping with an engineered slope insulation system, or any additional R value added which could also have been done with simple rigid type insulation boards.
In early 2015 our customer had called with leaks to the low slope membrane - the ice dams were back. This is an important lesson in choosing the correct roof membrane, insulation, drainage, re-sloping and more. Had we been able to re-slope the roof and been able to add insulation value, the heat from the inside of the home would not escape and get to the underside of the roof membrane and cause ice damming. But, the customer requested the least expensive options and even though our reports (see link above for sample quotation and inspection report) explain in detail most considerations, this is the way it was requested to be done by the customer.
So this spring we returned to find the same ice damming causing issues with a now new membrane. We also found drainage issues which were expected - the roof was ponding because a re-slope was not in our scope. And there were some technical (debatable) installation tweaks that may or may not have been required. Nonetheless, we now had a new roof leaking the year after it was installed.
So of course we once again suggested the upgrade options to alleviate the issue but the customer would have nothing with that and requested we simply do the repairs and move on.
Below is an account from the crew of the type of repairs they did to try and mitigate any issues in the future (full well knowing that the prime aggravating factors are insulation value and sloping).
May 5, 2015: Crew Attends to Residential Flat Roof Repair.  We arrived on site at 9:58. We started the day with the toolbox meeting and safety documents. We then went up on roof to determine an installation plan. The scope of work we decided on and did is as follows.
Scope of Work # 1 The first step was to pull all EPDM down to flat roof from under the shingles at the bottom of the sloped roof. This reinstall was to ensure no water could be coming from the flat roof to steep pitch roof transition. We then had to remove all metal flashing from around the two skylights and chimney on the roof. Once we had all the EPDM pulled we started lifting shingles along the first few rows of the sloped roof and applied the EPDM bonding adhesive. This was done under the first couple layers of shingles and to the underside of the EPDM. We then installed the EPDM back under the shingles. Then next step was to apply a bead of water block on the edge of the EPDM under the shingles. Once that was complete we secured EPDM by screwing a piece of turn-bar down on the edge of the EPDM where the water block bead was applied.
Scope of Work # 2 The crew arrived on site at 1 pm and started working on the cricket behind the chimney.  He started by cutting a piece of EPDM 7'x3'. He then had to take the Epdm bonding adhesive and apply in the same manner as the work in scope # 1 by applying the adhesive under the shingles as well as the under side of the Epdm. Once the 7'x3' piece was installed he started working on the corners. Using quick prime and seam tape he seamed in the corners of the Epdm around the chimney.
 
WORK LEFT TO DO: -patch corners -more turn bar and water block -install and or replace shingles Roughly 6 hours of work left to complete.
MATERIALS USED: -7'x3' piece of EPDM -EPDM bonding adhesive 1/3 of a pail -screws -30 ' of termination bar - 2 tubes of water block -tube of caulking for skylights -half a tube of lap sealer for temporary seals -6 feet of seam tape - quick prime 1/8th of a pail.
Residential Flat Roof Repair Edmonton. Pulling EPDM out from under shingles.
Residential Flat Roof Repair Edmonton. Pulling EPDM out from under shingles.
Peeling back Epdm membrane from skylight curbs.
Peeling back Epdm membrane from skylight curbs.
Taking flashing off chimney
Taking flashing off chimney.
Applied EPDM Adhesive
Applied EPDM Adhesive.
Rolling EPDM back under shingles after adhesive was applied.
Rolling EPDM back under shingles after adhesive was applied.
Installed Piece of Termination bar on tup edge of EPDM (under shingles)
Installed Piece of Termination bar on top edge of EPDM (under shingles).
joining two seams of EPDM, with quick prime and seam tape
Joining two seams of EPDM, with quick prime and seam tape.
May 8, 2015: Residential Flat Roof Repair Crew Attends.
We started at 7:30 AM with a daily tool box meeting. We then got up on the roof and started shoveling snow away from work area so we could complete today's scope of work.
Scope #1. Scope one consisted of applying corner patches to the rear corners of the chimney. The next step was to apply tape primer to the EPDM surface on the corner of the chimney. We then cut 6"×6" squares of 6" covers strip  to use at the corner patch.  We applied  this piece on top of the tape primer and let it sit to cure.
Scope #2. Install termination bar for the EPDM on the front of the skylights. For this we measured and cut a piece of turn bar to fit the front side of the sky light. We then screwed (mechanically fastened) the termination bar.
Scope #3. We had to take the bottom two layers of shingles off and replace with new ones. For this we had to carefully lift the bottom rows of shingles and pry out the nails so the shingles would slide out. We then took the new shingles and installed them. This consisted of laying down the first layer and nailing in place. The next step was to put on the second row of shingles which slid under the old existing one and nailed in place half way down the first shingle we layer down. Job is complete.
Completion photo #1 of where shingles at steep pitch meet low slope EPDM membrane.
Completion photo #1 of where shingles at steep pitch meet low slope EPDM membrane.
completion photo #2
Completion photo #2.
Materials Used:
-2 bundles of shingles
-roofing nails
-8'of turn bar
-2' of cover strip
-rags
- tape primer
-screws

< End of report >

Click here to visit our local roof repair website and order a quotation for flat roof repair in Edmonton or area or contact us per below.

CONTACT US
Call our 24 Hour Emergency Roof Repair at 1.780.424.7663. Mail to: 3428 99 Street NW Edmonton, Alberta T6E-5X5.
For all other areas of Canada call 1.877.497.3528 Toll Free.
We service all of Alberta including Edmonton, Stony Plain, Spruce Grove, Fort Saskatchewan, St Albert, Sherwood Park, Leduc, Nisku, Beaumont, Lac La Biche, Grande Prairie, High Level, Westlock, Slave Lake, Edson, Drayton Valley, Devon, Camrose, Wetaskiwin, Tofield, Lamont, Morinville, Vegreville, Tofield, Millet, Calmar, Evansburg, Redwater, Onaway, Viking, Athabasca, High Prairie, Valleyview, Fairview, Peace River, Whitecourt, Mayerthorpe and many more rural areas and towns.
  Code: 10007

Roof Eavestrough Repair and Waterproofing, June 3, 2015

ARTICLE: Eavestrough Repair Edmonton, Alberta. Installing Drip Edge for Proper Waterproofing at Fascia to Gutter Area. Installing Downspout Extensions for Drainage From Basement. Replace Damaged Downspouts.

Eavestrough Repair Edmonton. How to Maintain Your Eavestrough and Downspouts for Effective Building Envelope Water Proofing and Foundation Waterproofing. 

The scope of work for this work site covered a number of waterproofing essentials. The primary waterproofing issues that were fixed were:

1. Foundation Waterproofing. The objective being terminating water away from your foundation for proper drainage and extending the life span of your basement.

To effectively waterproof your basement you must have a yard that is sloped away from the basement and you must also terminate roof rain water away from the foundation of your building.

In this instance the crew installed downspout extensions to achieve the goal.

2. Building Envelope Waterproofing. A. The objective in this instance is for rain water coming down the slope of the roof to terminate in the eaves-trough and not run between the fascia and gutter. B. The secondary objective is to prevent ice dams that build up in gutters to creep up under the shingles and on to the roof deck causing deck rot and possibly leaks.

A. When water comes off the roof and misses the gutter and goes between the gutter and fascia it may cause problems with your foundation and may cause ice dam problems or water ingress in to your soffit area. This can rot out your roof assembly at the soffit and fascia area.

To correct this our crew installed roof eave edge drip flashing along the length of the eave deck sheathing. This will cause the rain water to terminate in the gutter instead of running between the gutter and fascia.

B. Installing drip edge will also help (nominally) ice dams not get to the sheathing and rot out the roof deck. For optimum waterproofing at the eave edge you would want to install ice and water membrane on the sheathing so that if the ice from the gutter gets up and under the shingles and over the drip edge and on to the sheathing and melts then the ice and water underlay will protect the sheathing and avoid leaks. In this example it was not in our scope of work.

May 21, 2015: Crew Attends Site for Eaves-trough Maintenance and Waterproofing Tasks.

Site Location: 16310 Stony Plain Road Edmonton, Alberta.

Location Type: Commercial, Institutional.

3:30 pm we arrived on site. Performed safety protocol and site meeting.

SCOPE OF WORK: We installed 80 feet of drip edge metal flashing along the south side of the building (by the side entry) as well as to the north side of the building. To install the drip edge flashing we used roofing nails to secure the drip edge flashing to the deck side of the eave edge of the roof to allow for water run-off to enter gutter. The problem the customer was experiencing was water running down the sloped roof and getting between the gutters and the fascia and not actually getting in to the gutters.

After that was complete the next scope of work was install downspout extensions and to build brackets out of wood to help the down pipes stay off the ground. The extensions will now run the water away from the foundation of the property. For the brackets we cut and measured pieces of wood to rest the down pipe on. Once these were built we painted them brown to match the down pipe.

We also had to replace two pieces of down pipe as they were damaged .

6 pm leave site.

Insatlled Drip edge
Installed drip edge flashing to ensure water got from sloped roof to gutter instead of running between roof edge and fascia.
wooden brackets we had to make for down pipe
Wooden brackets we had to make for down pipe. Water now terminates toward a slope and away from foundation for proper waterproofing.

Man hours:  7 hours Materials used: 10 pieces of metal drip edge. 2 down pipes that we replaced. 6  2 x 3 (boards) for downspout extensions. Spray paint for downspout extensions. 100 roof nails.

OTHER PHOTOS FROM JOB

< End of Report >
CONTACT US
Call our 24 Hour Emergency Roof Repair at 1.780.424.7663. Mail to: 3428 99 Street NW Edmonton, Alberta T6E-5X5.
For all other areas of Canada call 1.877.497.3528 Toll Free.
We service all of Alberta including Edmonton, Stony Plain, Spruce Grove, Fort Saskatchewan, St Albert, Sherwood Park, Leduc, Nisku, Beaumont, Lac La Biche, Grande Prairie, High Level, Westlock, Slave Lake, Edson, Drayton Valley, Devon, Camrose, Wetaskiwin, Tofield, Lamont, Morinville, Vegreville, Tofield, Millet, Calmar, Evansburg, Redwater, Onaway, Viking, Athabasca, High Prairie, Valleyview, Fairview, Peace River, Whitecourt, Mayerthorpe and many more rural areas and towns.

Roof Deck Drainage and Waterproofing

ARTICLE:  Roof Deck Drainage Problems. Waterproofing a 2 Ply SBS Modified Bitumen Roof Balcony in Edmonton, Alberta.

Recommendations for Waterproofing Outdoor Decks Over Conditioned Living Space. Roof Deck Drainage and Waterproofing - Inspection and Repair of a Torch-On Flat Roof on Outdoor Balcony at Multi-Family Condominium. Customers regularly call on us to have roof assessments (inspections) completed. During a roof assessment our journeyman roofers assess the roofs condition. We assess the roof for preventative maintenance reasons as well as inspecting existing problems that the customer is pointing out. We then discuss different scopes of work fix the problems as well as potential materials and costs related to the repairs. One of the most common calls we get for inspections and repairs are rooftop decks, balconies and patios. The primary reason the failure rate on rooftop decks is so high is because of the original installation. It is common for incorrect membrane choice to be the reason. In other words, many people install an outdoor deck membrane that is intended only for an outdoor deck and not a membrane for over a heated living space. If your rooftop deck or balcony is over a heated living area you require a special membrane that is also intended for low slope roofing (as well as deck waterproofing) and is approved for use over a conditioned living space. Common products for this are Dura-Deck or DecTec, both of which are a PVC membrane that are suitable to be walked on (so they do not require a floating deck over top) and they manufacture membranes suitable for over a conditioned living space. We use DecTec extensively and have had great results with it. Or, also common is the installation of a membrane that won't hold up to the foot traffic associated with outdoor living areas. Other reasons include simple age, wear and tear, drainage and issues relating to penetrations or floating deck assemblies on top of the membrane. Visit our main website for more information on rooftop deck waterproofing. This particular inspection and subsequent repairs was more focused toward an aging membrane and the associated repairs that come with not properly maintaining the deck membrane and building envelope over the years. The drainage problems were causing significant damage to the exterior of the building. Below you will find the inspection report. May 20, 2015: Journeyman Superintendent Attends for Balcony Inspection. Roof Inspection Location: 10245 116 Street NW Edmonton Alberta. Roof Inspection Date: May 20, 2015. Roof Type: SBS 2 Ply Modified Bitumen Torch-On Membrane on Roof Balcony. Site Location Type: Multi-Family Condominium.

This customer is experiencing a problem with water getting in the roof system and it draining out on a low corner and destroying some exterior brick work. In the area of the leak there are 2 laps of the SBS modified bitumen that have come apart.

Roof Deck Drainage damaging exterior of building. Edmonton, Alberta.
Roof Deck Drainage damaging exterior of building.
SBS Torch ON Seam Pealing back
SBS Torch-On lap pealing back.
SBS Torch on roof, seconf lap starting to come apart
SBS Torch on roof, second lap starting to come apart.
 

Scope: To repair this, degranulate the area and apply new torch-on stripping in and around the corner to seal in properly. Man hours: To complete 3 - 6. Material needed: 1 roll of SBS modified cap membrane.

The customer  would also like a quote for the following scope: to fill 13 pitch pockets on the roof and also seal the voids around pitch pockets with some detail sealer.

Area that needs sealing
Area that needs sealing at gutter to wall area.
Pitch Pockets that need filling
Pitch pockets at deck railing post termination area that need filling.
More seams on the sbs torch on roof that need to be sealed
More seams on the SBS torch-on roof that need to be sealed.

Man hours to complete = 10. Material needed: 4 gallons of portable sealer. 1 box of IKO MS Detail.

More Reading:
http://www.jlconline.com/decks/waterproofing-a-rooftop-deck.aspx
https://www.grscanadainc.com/Rooftop_Deck_Waterproofing.html
https://www.grscanadainc.com/DecTec_Deck_Waterproofing.html
http://www.dec-tec.com/
https://www.pinterest.com/generalroofing/dectec-deck-and-rooftop-waterproofing/
File to be updated when repair reports come in to office.
< End of report >
CONTACT US
Call our 24 Hour Emergency Roof Repair at 1.780.424.7663 Mail to: 3428 99 Street NW Edmonton, Alberta T6E-5X5.
For all other areas of Canada call 1.877.497.3528 Toll Free.
We service all of Alberta including Edmonton, Stony Plain, Spruce Grove, Fort Saskatchewan, St Albert, Sherwood Park, Leduc, Nisku, Beaumont, Lac La Biche, Grande Prairie, High Level, Westlock, Slave Lake, Edson, Drayton Valley, Devon, Camrose, Wetaskiwin, Tofield, Lamont, Morinville, Vegreville, Tofield, Millet, Calmar, Evansburg, Redwater, Onaway, Viking, Athabasca, High Prairie, Valleyview, Fairview, Peace River, Whitecourt, Mayerthorpe and many more rural areas and towns.
 

Edmonton Flat Roof Drain Installation, July 2013

GRS returned to a roof recovery job performed the year prior, when we recovered a tar and gravel roof with a new EPDM system. The client was worried about water ponding and reached out to us for quotation on drain installation. The client reached out to us to address water ponding on their flat roof, recently recovered with EPDM. There is 4-5 inches of standing water atop the roof for many days after rainfall, and would like to know what options are available for drainage to prevent structural strain. We sent out one of our journeymen to inspect the site, and their recommendation was that we install two drop drains and one scupper to facilitate better drainage. One of the problems observed by the crew member is that the dimensions of the house require eight feet of slope to properly drain the roof, something obviously not present in the flat-roof system as it is. Shortly after assessment, we provided the customer a quote for drain installation (two drop drains and one scupper). The client agreed and we set out the following day to carry out the intended work. Note: When attempting roof recovery, GRS notes that the existing roof is resurfaced as-is, unless you opt for re-engineering of the existing slope (typically more common with replacement, rather than recovery jobs). Whatever water ponding that was present before the recovery will be present after! IMAG0256 IMAG0258 IMAG0257 IMAG0255 IMAG0322 IMAG0323 IMAG0324 IMAG0325-1 IMAG0325 IMAG0326 IMAG0327 IMAG0328 IMAG0329 Field Report, July 19 2013: We went back to the residence the following morning for 7:30am, and work carried on through to 1:00pm. The servicing technician installed both requested drains (one 3" flat aluminum, the other as 4" flat aluminum). The scupper drain (6" x 4") was also installed with U-Flow clamps. We needed to wait for the proper colour of downpipe to accompany the scupper, so arrangements were made with the client to return within a few days once the pipe has arrived. (Update July 21, 2013: Downpipe received and installed.) < End Report > CODE: 14014 Contact Us Call our 24 hour emergency roof repair at 1.780.424.7663. Mail to: 3428 99 Street NW Edmonton, Alberta T6E-5X5. We service all of Alberta including Edmonton, Stony Plain, Spruce Grove, Fort Saskatchewan, St Albert, Sherwood Park, Leduc, Nisku, Beaumont, Lac La Biche, Grande Prairie, High Level, Westlock, Slave Lake, Edson, Drayton Valley, Devon, Camrose, Wetaskiwin, Tofield, Lamont, Morinville, Vegreville, Tofield, Millet, Calmar, Evansburg, Redwater, Onaway, Viking, Athabasca, High Prairie, Valleyview, Fairview, Peace River, Whitecourt, Mayerthorpe and many more rural areas and towns.

Residential Flat Roof EPDM Installation in Edmonton AB, June to July 2013

Below you will find a series of reports and photographs from the Edmonton roofing repair crew for an EPDM installation on a residential flat roof. Drain and flashing installation was also added to the roof replacement package. The client initially had a tar and gravel system. Site Preparation, June 23 2013: Gravel removal was finished in preparation of tomorrow's EPDM installation.
IMAG0275
Gravel removal
June 30 2013: The EPDM re-roofing has begun.  The client also made us aware that they had paid for another drain installation. We will return next week to do a metal and drain replacement.
IMAG0422
Laying down insulation
IMAG0420
Roof surface adhesion
IMAG0416
IMAG0419
EPDM fastening
IMAG0417
Mid-installation
IMAG0415 July 1 2013: The skylight, flashing, and drain need replacement or reinstallation. The client approved our use of the front lawn for doing our work on that side of the house. July 2 2013: The EPDM re-roof is now complete. Remaining tasks include drain installation on the rear roof, skirt flashing (skylight, chimney), and installing perimeter metal. IMAG0440 IMAG0441 IMAG0442 IMAG0443 IMAG0444 IMAG0445 IMAG0446 IMAG0447 IMAG0448 IMAG0449 IMAG0450 IMAG0451 IMAG0452 IMAG0453 IMAG0454 IMAG0455 IMAG0456 IMAG0457 IMAG0458 IMAG0459 Rear Drain Installation IMAG0479 IMAG0480 IMAG0481 IMAG0482 IMAG0483 IMAG0484 IMAG0485   < End Report > Code: 140 Contact Us Call our 24 hour emergency roof repair at 1.780.424.7663. Mail to: 3428 99 Street NW Edmonton, Alberta T6E-5X5. We service all of Alberta including Edmonton, Stony Plain, Spruce Grove, Fort Saskatchewan, St Albert, Sherwood Park, Leduc, Nisku, Beaumont, Lac La Biche, Grande Prairie, High Level, Westlock, Slave Lake, Edson, Drayton Valley, Devon, Camrose, Wetaskiwin, Tofield, Lamont, Morinville, Vegreville, Tofield, Millet, Calmar, Evansburg, Redwater, Onaway, Viking, Athabasca, High Prairie, Valleyview, Fairview, Peace River, Whitecourt, Mayerthorpe and many more rural areas and towns.