Flat Roof Repair Calmar Alberta, June 4, 2015.

Article: EPDM Flat Roof Repair Calmar Alberta, Commercial Building, Slope Toward Drains.

Below you will find a report from the flat roof repair crew. The issue with this roof was that a back-slope was required to get the water drainage correct. Once the back slope was installed on the flat roof the water drained from the roof much better. May 9, 2015: Crew Arrives to Complete Repair 
EPDM Roof
This EPDM roof had significant water ponding at the edges and drainage issues. 
Water Pooling
Technicians removing water from the roof to prepare for the back-sloping.
Installing EPDM
Installing EPDM over newly sloped area for more effective water drainage.
EPDM Repair
EPDM Repair in progress. Installing a back-slope at the roof parapet to redirect water to drain.
  After filling out our safety documentation and a weekly safety meeting we went up on the roof to find about 2 inches of standing water along the back wall. We spent 2 hours getting the roof dry. Once the roof was dry we then installed our slope with screws and plates to correct the roof ponding issues. After that we put 3 inch seam tape around the perimeter of our back slope. Once that was complete we put latex in our rubber using 2  pieces as one piece. It would of been a hassle after we glued our rubber down. The crew then glued it to the seam tape all around to ensure a 100% seal. The slope turned out really good. The customer inspected the work and was happy. I also noticed 2 outside corners that where failing so I fixed them while I was there we then packed up our tools downloaded them to the truck and left site at 5 PM. More Photos of Completion of Roof Re-Slope Repair. 
EPDM Flat Roof Repair
Applying an EPDM patch to a failed corner.
EPDM Repair
EPDM Repair completed - back-slope at parapet wall completed to ensure positive drainage of this flat roof.
  < End Report > Code: 5120 Contact Us Call our 24 hour emergency roof repair at 1.780.424.7663. Mail to: 3428 99 Street NW Edmonton, Alberta T6E-5X5. We service all of Alberta including Edmonton, Stony Plain, Spruce Grove, Fort Saskatchewan, St Albert, Sherwood Park, Leduc, Nisku, Beaumont, Lac La Biche, Grande Prairie, High Level, Westlock, Slave Lake, Edson, Drayton Valley, Devon, Camrose, Wetaskiwin, Tofield, Lamont, Morinville, Vegreville, Tofield, Millet, Calmar, Evansburg, Redwater, Onaway, Viking, Athabasca, High Prairie, Valleyview, Fairview, Peace River, Whitecourt, Mayerthorpe and many more rural areas and towns.

Rooftop DecTec Installation, March 2014, Edmonton

This client's residence bears a flat roof with a leak in one corner of the tar and gravel system. Upon GRS' inspection, however, the client desired to explore options for a total roof replacement and its conversion into a rooftop deck. Continue reading Rooftop DecTec Installation, March 2014, Edmonton

Edmonton EPDM Roof Recovery, July 2012

Below you will find the report for an EPDM re-roofing effort GRS undertook for one of our Edmonton clients. Their existing tar and gravel roof is in need of some work, so we quoted cost for repair, replacement, and recovering services before the client elected to recover the existing roof with EPDM. Our office thought it would be best to establish the scope of the work and inform the customer of what we intended to do at their location. Below is a summary of the correspondence from our team that outlines the project details. Project Scope, July 3, 2012: We will first order the engineered insulation package for the project, and the arrival of this will (in large) determine the effective start date. The best estimate for now is that we can begin late next week (July 11-13), but we promised to keep the client in-the-know if any updates were to come about. The client's on-site contact will be instructed to put a "walk in" bin on street (to allow for us to wheel in wheelbarrows of gravel from the street level); if there are any issues with that he'll let you or I know. We promised to put down sheathing that would safely allow wheelbarrows to be repeatedly rolled across the grass without damaging the property. Another member of the project team will contact the client with respect to colour swatch and choice for metal. They will be advised to keeping the face as low profile as possible, considering the raised elevation view due to sloped insulation raising the parapet. The roofers will be advised that we will be doing an EPDM recovery (removal of gravel first leaving the existing assembly), taking core samples to ensure insulation is dry, and that we are building up parapets to allow for sloped insulation. Finally, the job will require the removal of the flashing around the chimney and possibly require a re-flash (to be evaluated at the appropriate time). Materials:
  • (2) Spud bars.
  • Saws-all.
  • Cordless drill, charger, & extra battery.
  • (2) Push brooms.
  • Trowels.
  • WD-40.
  • (4) High Build 200.
  • (3) Jute mesh.
  • (2) Plastic cement.
  • (6) 6" rolls scrim.
  • (4) 4' rolls scrim.
  • Mastic.
  • Bag of calcium.
  • 5 Gallons of Varsol/Mineral spirits.
  • (2) Rolls duct tape.
Field Report, August 13 2012: The crew met with the two new members, and began working on gravel removal from the roof. First, gravel was shovelled into easily-managed lines on the roof, and was then loaded into the smaller buckets. The buckets were brought to the edge of the roof, lowered to ground level, and put into the wheelbarrow. One member would ferry the gravel into the disposal bin and return for the next load. Once the gravel was removed, existing nail holes in the flashing were filled with caulking to make a watertight seal while the rest of the crew cleaned up the site for the day. IMG_1421 IMG_1422 IMG_1423 IMG_1424 IMG_1430 IMG_1432 IMG_1433 IMG_1434 IMG_1435 IMG_1436 IMG_1437 IMG_1438 IMG_1439 IMG_1441 Field Report, August 14 2012: Prior to arriving at the worksite, our team went to the local shop to procure supplies needed for the day. The first store did not have everything necessary, so a detour was made to ensure that the remaining materials were purchased and brought to the client's residence. They began preparing the roof for the day's work when the weather conditions rolled in that would've made the work perilous. The crew left the site for the day. NOTE: The in-progress field reports will be inserted here as content is moved over from the old system. This will cover the EPDM installation, re-sloping, and other site details. - Please accept our apologies for the temporary omission! Field Report, September 11 2012: Today, the crew installed two scupper drains on the south-facing parapet of the roof. This will accommodate for better water drainage and lengthen the life of the newly-installed system. New sheet metal was installed to the parapet, as well as the drop-drain near the garage with a downpipe. photo (38) photo (39)-1 photo (39) photo (40) photo (41) photo (42) photo (43) photo (44) photo (45) photo (46) photo (47) photo (49) photo (50) photo (51) photo (52) photo (53) Field Report, September 12 2012: The GRS team finished up the job, by installing two new caps for the vents, two new caps for the scuppers, and the two downpipes for the scuppers installed the day before. Everything is clean, level, and to GRS' exacting standards for project success. photo (54) photo (55)photo (65) photo (64) photo (63) photo (62) photo (61) photo (60) photo (59) photo (58) photo (57) < End Report > CODE: 9528 Contact Us Call our 24 hour emergency roof repair at 1.780.424.7663. Mail to: 3428 99 Street NW Edmonton, Alberta T6E-5X5. We service all of Alberta including Edmonton, Stony Plain, Spruce Grove, Fort Saskatchewan, St Albert, Sherwood Park, Leduc, Nisku, Beaumont, Lac La Biche, Grande Prairie, High Level, Westlock, Slave Lake, Edson, Drayton Valley, Devon, Camrose, Wetaskiwin, Tofield, Lamont, Morinville, Vegreville, Tofield, Millet, Calmar, Evansburg, Redwater, Onaway, Viking, Athabasca, High Prairie, Valleyview, Fairview, Peace River, Whitecourt, Mayerthorpe and many more rural areas and towns.